Delivery of equipment for construction

On the 28th of January 2021 first batch of equipment for the construction of the mobile hybrid power plants is delivered to Tabalakh (Ulakhan-Kyuel), Republic of Sakha (Yakutia).

Delivery is done by trucks on frozen rivers from the company's warehouse in Nizhniy Bestyakh in extreme cold temperatures as low as -60 °С. The route distance from Nizhniy Bestyakh to Tabalakh is 1350 km. In total it is planned to transport 480 tonnes of equipment to the construction site. The transportation of this equipment is planned to be carried out by KamAZ 43118 Saigak and Ural 4320 trucks, which take 5-6 days one-way. All equipment will be delivered to the construction site by the end of March 2021 before frozen river route closure.